PSEG North Central Reliability Project

Project Details:

Project Owner:  PSE&G
Project Client: Matrix NAC, Eddystone, PA
Project Cost: Over $10 million
Project Duration: 18 months

Project Challenges:

The project required working around existing utilities in order to tie the new electrical yard in with the existing facilities.  The project required significant manpower and resources to meet an aggressive project schedule.

Work Performed:
  • Site Clearing and Excavation to subgrade the new electrical yard
  • Installation of new concrete foundations
  • Installation of new below grade utilities
  • Yard grading and asphalt paving
  • Modular Block Retaining Walls