Project Details:

Project Owner: IMTT Inc.
Project Client: IMTT Inc.
Project Cost: Approx. $230,000
Project Duration: 2 Months

Project Challenges:
  • Tight Work Area
  • Coordination with Facility Operations for all work activities based upon Terminal Operations
  • One of the RIngwalls was required to be constructed beneath a suspended tank
Work Performed:
  • Excavation
  • Formwork
  • Reinforcing Steel
  • Concrete Placement
  • Backfill and Site Restoration