Wilmington Garage Replacement Early Site Development

Project Details:

Project Owner: Christiana Health Care System
Project Client: The Whiting-Turner Contracting Company
Project Cost: $1 million – $5 million
Project Duration: 10 months

Project Challenges:

The demolition of the existing parking garage and site preparation portion of the project had multiple logistical challenges . The schedule was aggressive and had to consider minimizing delays to the Hospital operations. Simpson & Brown and Whiting-Turner coordinated and executed a plan in order to install the new foundations. We successfully re-routed utilities, established pedestrian walkways, and installed a support of excavation allowing for up to 16 feet of cut from established grade.

Work Performed:
  • Site clearing and demolition
  • Earthwork and grading
  • Soil export
  • Sanitary sewer installation
  • Storm sewer installation
  • Water line installation
  • Installation of support of excavation system
    • Drilled soldier piles
    • Treated timber lagging
    • Drilled hollow bar
    • Tiebacks